PowerBI Progress & Schedule Dashboard – By Darrin Kinney

I have recently been developing a series of videos that highlight the key features utilized in a progress and schedule dashboard. The videos showcase the capabilities of PowerBI dashboards in the Project Controls space. I have not seen dashboards effectively used in this way and want to share the valuable knowledge.

 

I have recently been developing a series of videos that highlight the key features utilized in a progress and schedule dashboard. The videos showcase the capabilities of PowerBI dashboards in the Project Controls space. I have not seen dashboards effectively used in this way and want to share the valuable knowledge.

This series is not meant to be a step by step guide. There are subtleties about this demo that may cause difficulties in the production environment. I would simply recommend you share this with your development team and discuss the pros and cons of your approach. Oftentimes, a more straight forward approach is more valuable when compared to endless development polishing an inferior product.

 

Part 1: The Showcase

This video gives an insight into the key capabilities of the dashboard. Having the ability to seamlessly review schedule activities, and how these contribute to the overall progress and forecast, is invaluable.

The ability to quickly dive into your schedule, without having to deal with the confines and limitations of your actual scheduling tool are also key features.

 

Part 2: The Excel Feeder Sheets

This highlights a simple Excel feeder sheet. Too often the time phased data that our schedules produce are not easily accessible in a digital format. I have built an excel file around a typical structure that project controls deals with. This structure will lend itself nicely to the steps that follow in converting the into a database format.

 

Part 3: PowerBI PowerQuery

Here we import the data from the Excel feeder sheets into the PowerBI platform. The use of PowerQuery is so embedded with the way PowerBI works. The steps you need to follow here are the similar to the steps you would need to follow in inserting the progress and schedule data into any formal data structure. The way we think about data is sometimes not compatible with the format that databases need. This is specifically around the need to “unpivot” time phased data.

 

Part 4:  PowerBI Measures and Dax

With all the data now structured and available to PowerBI, we need to now dive into the use of DAX to create Measures. A perfect example in the use of measures is in the generation of progress curves.

What might seem line a straight forward approach to drawing simple progress curves, is in fact (within the realms of PowerBI) not that simple. However, if you follow a logic approach and know what calculations are needed, the world is your oyster.

 

Part 5: Integration of JIRA and Agile Methods

In the (as of now) final installment of this series, I showcase a way in which we can integrate our PowerBI dashboard with a JIRA project. This approach is completely different from what you might expect. I don’t want to put a PowerBI dashboard ontop of my JIRA task list. I want to put a JIRA task list on top of my schedule.

The purpose of the dashboard is to extract the SCHEDULE data from the scheduling tool. When variations to prior forecasts occur, or where further detail is needed, we are often constrained because pictures, running commentary and discussion about each activity is not something that resides in our schedule. However, we can use JIRA to easily capture those elements and use our PowerBI dashboard and a linking tool to integrate everything together.

 

The Future: ???

There are still a lot of features and extensions that I have yet to formally discuss. The next steps are likely going to be a showcase of a SQL Server backend for this data. There is a lot of information that is missed in the way this dashboard imports data (specifically past budgets). Therefore visibility into changes is restricted.

Another interesting feature is the use of saw tooth graphs when budget changes occur. I have a clear vision for how this is possible, but perhaps not the development know how. I will definitely be passing my ideas on to a few more tech savvy than I, and will hopefully have something to say about that in the near future.

In general, the way in which dashboards and data are embedded into our work processes, is a field ripe for growth. It is also an endeavor that can greatly increase the visibility into project controls data and can also bring teams together using integrated tools like JIRA. As such, the future is bright and where we should always have half an eye looking.

 

Agile in Construction

Will Agile ideas and approaches fit the construction world – Definitely.

This does not mean I think that a lot of the tried and true practices we have developed need to change. Quite the contrary, the construction world have for decades been the pioneers for quality project management.

What has changed is the way in which people communicate and the culture we live in. Agile does have a lot of good properties in the personal communication. So I believe the construction world needs to embrace some aspects of Agile and the software tools that have been developed to support Agile management

 

Introduction to Agile in Construction

In this presentation, we can see that indeed many of the terms used in Agile have existed for a long time in the construction PM space. So, in many ways, we already are Agile. Thus, if you go down a path to embrace new management approaches, you first need to understand the current overlaps and also where opportunities exist.

 

Using JIRA to improve communication on construction projects

There are some great possibilities in using JIRA in the construction world. I do not believe a typical Agile approach fits into the project space; however, many of the ideas are sound and specifically the tools that have been built to facilitate Agile can be molded to fit the construction project space.

Specifically, this relates to the way we communicate and track the work we are performing or the work we are overseeing. Applications such as JIRA and DevOPS have capabilities that I feel are a perfect match for the construction world and we need to be looking how we can customize these new tools to really revolutionize the way construction projects are managed.